Start-up checklist.
Operation
Note:
Your humidification system may not have all
of the options listed below. If an item does not
appear, skip to the next item and continue the
process.
Verify that wiring is done per instructions in this
manual and the unit wiring diagram.
Make sure that the keypad/display is not inside
the control cabinet.
Check water level control voltages. The reading
should be 2.5 VAC without water; and 0 VAC
with water from ground (Pin 33-J8) to probe
inputs (Pins 30, 31 and 32-J8).
Check the proportional band setting in the
“System Set Up” menu of the keypad/display
(default is 10%).
Check the cycle setting in the “System Set Up”
menu of the keypad/display (default is 60
seconds; 2 seconds for SSR).
Check the proportional gain setting in the
“System Set Up” menu of the keypad/display
(default is 80).
Check the integral gain setting in the
“System Set Up” menu of the keypad/display
(default is 40).
Check the derivative gain setting in the
“System Set Up” menu of the keypad/display
(default is 0).
Check drain duration (default is 8 minutes).
Check flush duration (default is 8 minutes).
Check RH setting.
Check control signal.
Check amp draw of heaters for electric units;
refer to wiring diagram for proper rating. If unit
is powered by steam, check for steam flow. For
gas fired units, verify gas flow and combustion.
Confirm that the control signal being connected
to the VAPOR-LOGIC
®
3
system is compatible
with the VAPOR-LOGIC
3
program. Identify the
VAPOR-LOGIC
3
program code on the wiring
diagram or on the outside of the control cabinet
door. Refer to the VAPOR-LOGIC
3
manual to
decipher the code using the nomenclature
description on Pages 8 and 9.